Hello,

We have a problem with the schedule.
On a team, it is planned at the beginning and end of the month but nothing in the middle.
By making a recalculation of the schedule the problem persists.
Yet activities are put in the middle of the month for this team.
How to fix this problem ?

Best Regards,


 
Posted : 16 Jan 2018 16H01
(@babynus)
Posts: 14952
Member Admin
 

Difficult to analyse with so few information.
Please post screen shots :
- planning
- some reporting such as "monthly planning resource/project/activity"


 
Posted : 17 Jan 2018 0H11
(@sogeti)
Posts: 135
Active Member
Topic starter
 

Hello,
I'm attaching reports to you with the imputation error.

We have another test server or on this one we recreated the ProjeQtOr database and the problem is solved.

I think the problem come from our base which had some problem of indexing.


 
Posted : 17 Jan 2018 12H23