Please see attachment. I setup Start-Start between 860-AP251: [P6 SCHEDULED] PQ Test Cases Execution (860-AP251.SP) and 860-AP251: Prepare equipment(s) for lockout/tagout (LOTO). The 860-AP251: [P6 SCHEDULED] ... (Manual planning) is a placeholder for the activity to execute. Whilst running the planning calculator, 860-AP251: Prepare equipment(s) ... (as soon as possible) start before. What should be the correct setup to have both always in sync ?
The Manual Planning is something that will have planning from some kind of Agenda, manually entered (thus name seems quite accurate).
So is is nonsense to try and move it with dependencies ...