Hi.
Few months ago I created an periodic meeting for two time period and I assigned five attendees to it.
Beginning of November I got a new employee as a team member and I assign new resource to this same periodic meeting.
What I can see is that PQ assign new resource to all scheduled meetings, past and future ones no matter which date is defined as newly added resource entry date as resource.
Result is that I see new employee as registered attendee for all meetings that happened before employee was in the company.
Any solution for taht?
Regards
You are right, new resource is assigned to all the meetings.
We'll improve this to add it only to next meetings, and only from his start date (if resource has start date)
Good.
Thanks.