Hi Expert,
I want to do planning utilizing only sunday off, but when after global parameter setting, I checked with input 2 days in duration for with input start date = 09/02/2022, it is not updating end date with 10/09/2022, but updating with 12/09/2022. (dd/mm/yyyy)
Please help me to understand above happening.
Please refer attachments.
Hello,
Did you change your global parameters settings to have only Sundays off and then directly fill in your activity duration (start date 09/09/2022 and duration 2 days)?
Therefore, you should disconnect and reconnect and it will work fine.
It worked, after disconnection & logged in again.