Hi,
I'd like to be able to change the WBS nuber of some activities in a project to have a planning with activities in the good order in function of the time to be done.
I've not found the solution in the online help.
I just beginn with projeqtor and my english is a little poor, sorry
Stéphane
Go to the planning view (with the Gantt chart).
There you can drag & drop tasks to reorder them : use "grapper" area in left most part of the line, with little grey points (your cursor will change when in the good area)
Thanks a lot for your help !! :woohoo: