Split activities
 
Notifications
Clear all

Split activities

2 Posts
2 Users
0 Reactions
5,118 Views
(@guest)
Posts: 120
Active Member
Topic starter
 
[#197]

How can I split one activity
I have one activity that is a long term activity and I assign a resource to this activity, then I have a new critical activity that I need to switch the resource to this activity and then go back to this activity

Regards


 
Posted : 17 Sep 2011 0H29
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Just create your new activity and set its planning priority to a lower value than the long term activity.
If you want to start new activity at a given future date, the best is to create a milestone as a "fixed" milestone to the given date, and define this milestone as predecessor of the activity.
Replan and you're in.
Regards.


 
Posted : 17 Sep 2011 1H24