Hello
we injected 192
activities en masse (all in the same form and with the same options)
they have been well generated in ProjeQtOr's "Activity" menu.
However, when we launched the "Project Planning Calculation" so that they appear in the employees' agendas, 52 of them are not planned!
Do you have an explanation? and what do we need to do to solve the problem?
for information: we tried again to run but nothing helps
Activities without assignments won't be planned.
Possibly, some of your activities don't have assignments.
Hello,
I have provided you with my import files. All the lines are identical, that's another problem.
cordially
Lines are not identical.
Responsible is different ...
The name of the person in charge is not in question and the date is also different but it is normal since one has different users and one wants to plan in mass ...
If I delete the activities, do not reuse the same structure and the same data and only 10, it works, but it is fast because I can not trust in the injection.
The name of the person in charge
Yes it is.
Because depending on the responsible, assignment may be created automatically.
It get to my first remark !:
Activities without assignments won't be planned.
Possibly, some of your activities don't have assignments.
As you don't add assignments, only activities with auto-creation of activities will ber correctly planned.
I can not trust in the injection.
Injection is not the source of the issue.
Understanding of what it invoilves and what impacts planning calculation is.