Hi,
In timesheet validation, there is a column with an expected number of hours for each resource.
These expected hours are not in sync with the employee contracts.
So, where can I set this expected number of hours for each resource / employee ?
Thanks
Franck
Hello,
Expected: corresponds to the number indicated on the “capacity (FTE)” resource multiplied by the number of days.
Have a nice day,