Forum

Setting Validate Da...
 
Notifications
Retirer tout

Setting Validate Date

4 Posts
2 Utilisateurs
0 Reactions
6,758 Vu
(@jstraight-griggs)
Posts: 8
Active Member
Début du sujet
 
[#2392]

Hi is there a function to take the planned dates and store to the Validate Dates fields (which I would consider equivalent to setting the baseline).
I searched the manual without success of finding this type of feature.
Thanks
Judy


 
Posté : 26/06/2015 6:02 pm
(@babynus)
Posts: 14952
Membre Admin
 

Hi is there a function to take the planned dates and store to the Validate Dates fields

Yes, there is : on planning screen, use button "store planned dates into requested and validated dates".
(on left side of print button)

(which I would consider equivalent to setting the baseline)

Exact !

I searched the manual without success of finding this type of feature

The user manual may not be up to date.
There is a complete refactor of user manual planned.


 
Posté : 29/06/2015 11:33 am
(@jstraight-griggs)
Posts: 8
Active Member
Début du sujet
 

Is there a task setting that is required for this function to work? I tried it on a 2 task test project and it copied the dates for one task, but not the other?
Thanks


 
Posté : 02/07/2015 4:39 pm
(@babynus)
Posts: 14952
Membre Admin
 

No, I can't remind any requirement tgo have it work.
Please give more hints to investigate.


 
Posté : 03/07/2015 6:27 pm
Share:
Retour en haut