New question
In admin mode I gave a task ("action") to Mr X.
When I connect a "Mr X" I see the task in "today" as responsible.
But I do not see the task in Work -> Actions.
This it is normal.
Posted : 06 Mar 2014 16H36
Mr X must be affected to the project to have access the elements.
Posted : 06 Mar 2014 16H57
Topic starter
OK this is good, it works
Posted : 06 Mar 2014 17H20