Hi,

I would like to suggest to enable text formatting (e.g. colour) and add column to indicate the tasks in the critical path (i.e. critical tasks) and tasks that are milestone tasks. It would be useful to quickly identify and filter by column to sort out the critical tasks and milestone tasks for viewing in the planning menus and pdf export.

I included the screenshots of the text colour formating and defined columns (critical tasks and milestone tasks) in MS Project as attached for your reference. Thanks!

Cheers,
Rainbow


 
Posted : 20 Jan 2021 5H19
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Request recorded as Ticket #5222


 