Hi,
as far as the progress, now is possible to insert the time left for each task and the progress % is automatically calculated.
Alternatively is it possible to insert the progress % and automatically calculate the time left?
Sometimes is easier to estimate the time left in %.
It would be appreciated to have both choices.
Regards
Alternatively is it possible to insert the progress % and automatically calculate the time left?
No
Sometimes is easier to estimate the time left in %.
Maybe easier but surely less accurate.
Thank you,
I know, please note that this is a feature present in all PPM tools, including the EV report.
Regards
Yes, it is present in most PPM tools ... as these tools don't really calculate planning.
They "draw" a beautifull gantt chart that is not linked to resource availability.
ProjeQtOr is not a PPM (Project Portfolio Management) tool.
It is a PM (Project Management) tool that includes PPM features.
But the basis of its design is the operational data : ProjeQtOr is designed by project leaders for project leaders and their teams.
And it manages a real "capacity planning".
This requires a work driven approach, and on this approach enter of left work is natural.
We can improve ProjeQtOr to introduce enter progress to define left, but we won't do this for free.
We'll wait until someone considers sponsoring this evolution.