import activity prize

3 Posts
2 Users
0 Reactions
2,283 Views
(@norbertd)
Posts: 68
Active Member
Topic starter
 
[#5262]

hello

i want to Import activity prizes for several Tasks. after starting the Import the error message is that a activity prize for this type (Task) Exists and so i have to confirm it.
in the form can i confirm this and activity prize is inserted. But the Import stops and the prizes are not inserted.

thanks

greetings
Norbert


 
Posted : 05 Jul 2018 18H36
(@babynus)
Posts: 14952
Member Admin
 

This occurs because you try and create dupliacte Activity Price (same project, same activity type).
This should not be allowed.
We allowed it through confirmation, to fit some need, but import does not take this into account.
What can be confirmed in interactive mode is blocking through import.

I don't see how to avoid this (we cannot manage confirmation for each line... and cannot manage global confirmation as subjet to confirm may be different for each line)
Only (dangerous) possibility is to implicitly confirm through import.
It is dangerous as it would concern all confirmations (some may set the mess if implicitely confirmed)


 
Posted : 05 Jul 2018 19H08
(@norbertd)
Posts: 68
Active Member
Topic starter
 

what a pity. that would save me lot of time.
maybe you rethink this issue.
thanks


 