Replanification doesn't take closed predecessors correctly into account

1 Posts
1 Utilisateurs
0 Reactions
2 Vu
(@arnpere)
Posts: 13
Active Member
Début du sujet
 
[#3999]

Hello,
I found a replanification bug that happens when an activity actually ends before planned date. Then its successors don't get replanned until its original planned end date...
Here's how to reproduce :
- create two activities A & B linked together in this order
- affect 5 days on a ressource on A, and 5 more days on activity B, then launch a planification calculation.
This results for example in activity A having plannedStartDate = 02/01/2017 and plannedEndDate = 06/01/2017
and activity B is planned afterwards : plannedStartDate = 09/01/2017 and plannedEndDate = 13/01/2017
- Now on 3rd of january, my ressource says activity A has needed 2 days and is now over (leftWork = 0), so activity is closed
- If you now relaunch a planification calculation, activity A doesn't get replanned, and as a consequence, activity B uses previous plannedEndDate as a (false) constraint and therefore remains planned starting 09/01/2017.


 
Posté : 10 Jan PM 21:011