Hi,
When work can no be planned on an activity; information is displayed in red in the assignement of adequate resource (number of days / hours that could not be planned).
However when I change the assigned work to the same resource and that I assign a correct effort (correct in the sense it could be allocated in the timeframe for this resource) and re-calculate the planning for the project / activity, the information on overallocation remains the same.
I have created example on demo site => Project "Project for issue on non planned work" / Activity "Task #1". (see attached screen shot)
Thanks
Stephane Pelletier
Issue confirmed : "not planned work" is not updated if there is not left work.
For information, I tried setting left work = 0,1 : the not planned work is then updated; but still with not planned work = left work as the resource has no availability...
Ticket #1886 recorded
