Hi,

V7.3.3

When i export a time sheet with the following settings, output is empty

Period to export: -- Selected Week
Resource to export -- Selected resource All resource does not work either

Selected month, year and get all are working fine

thanks


 
Posted : 19 Feb 2019 23H44
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Please post error traced in log file


 
Posted : 20 Feb 2019 12H26
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Seems to work fine on V7.3.5 😉


 
Posted : 20 Feb 2019 12H29
(@karl-binet)
Posts: 129
Active Member
Topic starter
 

Hi

Upgraded to V7.3.5

same issue

no error in log file

2019-02-21 04:03:17.899 ===== TRACE ===== NEW CONNECTED USER 'marco.rivalti' (using remember me feature)
2019-02-21 04:12:53.021 ===== TRACE ===== DISCONNECTED USER 'marco.rivalti'
2019-02-21 07:02:38.928 ===== TRACE ===== DISCONNECTED USER 'gpizzuco'
2019-02-21 07:02:42.404 ===== TRACE ===== DISCONNECTED USER 'karl.binet'
2019-02-21 07:02:47.839 ===== TRACE ===== DISCONNECTED USER 'ahoac'
2019-02-21 07:04:19.527 ===== TRACE ===== Login of non admin user during upgrade. User 'cboivin'
2019-02-21 07:04:35.857 ===== TRACE =====
2019-02-21 07:04:35.857 ===== TRACE ===== =====================================
2019-02-21 07:04:35.857 ===== TRACE =====
2019-02-21 07:04:35.857 ===== TRACE ===== DataBase actual Version = V7.3.3
2019-02-21 07:04:35.857 ===== TRACE ===== ProjeQtOr actual Version = V7.3.5
2019-02-21 07:04:35.857 ===== TRACE =====
2019-02-21 07:04:36.024 ===== TRACE ===== =====================================
2019-02-21 07:04:36.024 ===== TRACE =====
2019-02-21 07:04:36.024 ===== TRACE ===== DATABASE UPDATE COMPLETED TO VERSION V7.3.5
2019-02-21 07:04:36.024 ===== TRACE =====
2019-02-21 07:04:36.024 ===== TRACE ===== =====================================
2019-02-21 07:04:36.024 ===== TRACE =====
2019-02-21 07:04:36.034 ===== TRACE ===== === SCREEN CUSTOMIZATION ISSUE =====================================
2019-02-21 07:04:36.034 ===== TRACE ===== Certaines customisations d'écran ne sont pas cohérentes :
2019-02-21 07:04:36.034 ===== TRACE ===== - Projet
2019-02-21 07:04:36.037 ===== TRACE ===== Les customisations ont été corrigées automatiquement
2019-02-21 07:04:42.356 ===== TRACE ===== NEW CONNECTED USER 'karl.binet'
2019-02-21 07:06:55.227 ===== TRACE ===== NEW CONNECTED USER 'nsleclerc'
2019-02-21 07:08:56.052 ===== TRACE ===== DISCONNECTED USER 'karl.binet'
2019-02-21 07:08:59.175 ===== TRACE ===== NEW CONNECTED USER 'cboivin'
2019-02-21 07:09:18.819 ===== TRACE ===== DISCONNECTED USER 'cboivin'
2019-02-21 07:09:23.897 ===== TRACE ===== NEW CONNECTED USER 'karl.binet'
2019-02-21 07:10:39.155 ===== TRACE ===== DISCONNECTED USER 'karl.binet'
2019-02-21 07:10:44.690 ===== TRACE ===== DISCONNECTED USER 'nsleclerc'
2019-02-21 07:12:18.017 ===== TRACE ===== NEW CONNECTED USER 'karl.binet'


 
Posted : 21 Feb 2019 15H17
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Are you sure you have something to Export ?
Only real work entered is exported, so no entry menas no export...


 
Posted : 21 Feb 2019 23H35
(@karl-binet)
Posts: 129
Active Member
Topic starter
 

Hi, yes i'm sure, here is some more information

User Benoit Chauty
Week 7 from february 11 to 17

Timesheet

Here is the export for

Period = Selected months
resource = selected resource

Here is the export for

Period = Selected week
resource = selected resource

If it can help you in your search, while writing this post, out of the blue, i ran an export for select weeks/selected user and it work 1 time.

So since i started this post, i may have tried about lets say, 25 time, i had only i time the export gave me results. i can't realy figure out why.

Thanks


 
Posted : 22 Feb 2019 16H15
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

OK, I found use case to reproduce :

Use case to reproduce : 
 - open timesheet
 - open timesheet
 - export for "selected resource", "selected week" => OK export is correct
 - change resource in timesheet
 - change again resource to get back to previous one
 - export for "selected resource", "selected week" => KO export is empty


 
Posted : 23 Feb 2019 16H14
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Ticket #3865 recorded


 
Posted : 23 Feb 2019 16H14