Hi, Have you planned the pool on at least one activity? and then recalculated your project ?
Hello, This is an on-demand development. we will establish a quote provided that your needs are extremely well specified. Contact us in private on...
modes of planification get an order of priorization beetween them. Manual then regular then recurring then ASAP
Thank you, but what about the second sort ?
Hi, Could you tell me where do you find this kind of informations, which links are they coming from ? The good answer is the first sort.
Hello, Recurrent mode is a special mode planning each week, the same selected workload by day over a week, during the whole project. You can limit ...
it should be like that !!! it is weird.
HELLO, Yes he is not allocated automaticaly on parent project. you have to do it . On the other way from parent to sub project is automaticaly. ...
It's weird, it's true. We test it localy, there is no contamination beetween the sub and the under project as expected. You should investigate your lo...
What is the situation ? please tell me.
Last solution( rights you had set) ? You have the right to replanified but you do not have the right to modify activities.
Tickets are not managed as activies.... could be a lead.... but it doesn't give the final answer about our issu
It is weird ! anyway, they seem to be without any left work, could you reassigned as a test some workload on one activity and try to recalculate one o...
Are you sure they are not fixed ou on paused situation ? I m looking for a lead....
hi Could you try again on screen of Gantt view and not "project portefolio"