Critical resources explained

It's a question we already had some years ago and I don't want to waste time on that again. I'm introducing Projeqtor in other organizations and prop...

10 months ago
Reply
Critical resources explained

Possibly a training course ? Or just a better manual.

10 months ago
Reply
Changing title and translations for "planning activity" flag for tickets

I'm speaking of the activity card (as written in the original post). When you are in the activity card (not on a ticket card) "planning activity" is ...

10 months ago
Reply
Calendar Easter monday (and other problems)

We see Easter Monday is already added automatically with Easter. Other two problems still remain.

11 months ago
Reply
[SOLVED] Milestones crossing projects

Sorry, I tried everything but projects. Using link to projects it works across projects.

11 months ago
Reply
[SOLVED] Milestones crossing projects

Sorry, duplicated post. Please. delete it,if possible.

11 months ago
Reply
Changing title and translations for "planning activity" flag for tickets

"Planning activity" is too generic. "Tickets planning activity" is easily understandable.

11 months ago
Topic
Replies: 1
Views: 430
Topic
Replies: 5
Views: 617
Topic
Replies: 1
Views: 147
Topic
Replies: 2
Views: 592
Reply
A quick way to count activities per project

Thanks for your clarification. I though that data displayed on "today screen" were strictly inherent to the logged person. But I would like this coun...

1 year ago
Reply
Activity type: task or development?

I understand your answer and agree with it, but sometimes documentation may be misleading:

1 year ago
Reply
A quick way to count activities per project

Today screen is a personal view, We need it on the projects screen, which is a general view.

1 year ago
Topic
Replies: 2
Views: 441
Topic
Replies: 5
Views: 567
Reply
Background activity setup - bg stops after two minutes

I think that is deeply wrong, Ok, don't want to start a war. When I will have time I will implement it. Regards.

9 years ago
Reply
Background activity setup - bg stops after two minutes

(real) cron is the only affordable solution, just need two lines of comment and it's done. Windows users may use actual scheduler as alternative, but ...

9 years ago
Reply
Background activity setup - bg stops after two minutes

Of course php is not permitted to set itself for infinite loop. This is a normal safety precaution. Wouldn't it be easier to provide a cron php file ...

9 years ago
Topic
Replies: 1
Views: 3043
Topic
Reply
Italian translation in lang.xml messed up

Now it is correct, at a quick look. Version I've found before had the last version row tagged as 6.0.0.

10 years ago
Topic
Replies: 2
Views: 3084
Reply
Permissions for an external worker

It is correct a responsable can make changes, I would like to avoid changing responsable permission only for limiting an external resource. I'll expe...