Last seen: 06 Nov 2013 17H36
Ta date de congés glisse au 14/2 alors que tu as demandé qu'elle se termine le 7/2 => Donc l'activité passe en rouge ++
Bonjour, Tu assignes tes activités avec des ressources et lorsque tu lances la planification en fonction des dépendances, mode de planification, pr...
Ok, Problem 1: What I do not understand is that during the month of February to early March there are activities 1, 2, 4 => There is the problem...
Hi, I completed the document Problem 1: Add the workload for 3 months. We see that shift 1.4 days because of rounding Problem 2: I added a vie...
Hi, I completed the document Problem 1: Add the workload for 3 months. We see that shift 1.4 days because of rounding Problem 2: I added a vie...
Yes you can, however it seems to me the ID (XXXX) at the end? [PROJ]-TYPE]-XXXX-HWArchitecture => [PROJ]-TYPE]-HWArchitecture-XXXX
It's already done. Just to clarify in global parameter {PROJ}-{TYPE}- and specify the number of digits (4 for me). Results for each document: {PROJ...
Ok I understand. I'm planning to test this week, to make sure the behavior is OK. If it's OK, I'll create in the user menu (profile CDP) can choose ...
Yes it is a solution! Easy to implement in the code? But why not give priorities to manage the priorities of different planning mode?
I agree with you but : When current delivery is late, the CDP must prioritize the technical activities. The "transverse" activities become less pri...
I agree 😉 But it would be nice automatically adjust :silly:
Thanks, Some users use multiple products, I would like to see the related product version in parentheses ex: Version 5.3 of the product "Toto" To...
you're right I had not thought about the external project solution Tanks for your support 😉
This is the profile admin who does not see the top of the project I acord with your vision constraints do not see the top projects if it is not af...
This bug is related to the profile => Only admin profile encounter this problem. Strange ?
3) Change the combo box "project" views activities, project milestone, ... that which manages the project (top left). Objective: To limit the list of ...