Last seen: 17 Oct 2018 15H56
Hi, I have the solution, it's only " activate/desactivated auto calculation " on gantt is not validated and now it's OK, but this choice modify my ...
V7.0.9 is installed, same problem 🙁 Could you send to me yours all global parameters ? And how have you some colors on the gantt ? Thanks.
Erratum, No, it's ok on your site.... 🙁
Hi, Project : toto_test-jcro After test: same problem
yes, but with which account for access at : ressources/real work allocation/ activites / Thanks.
Yes, it's Strange. This problem is arrived with the lasts versions before all was correct :(. I check the global parameters but i think all are OK. ...
FTE = 1 in this detail for this ressource
And for information the definition in parameter of the work time projeqtorworktime.docx
See detail in file attached for this example 2days 0,5 real work alloction Version Projeqtor V7.0.8 projeqtor_assignation.docx
Hi, Where is FTE value ?
Hi, I create only an activity on 2 days by example After , i allocated a ressource for 2 days After in the real work allocation , i have imputed ...
Hi, Sample with doc see attached Thanks gantt2.docx gantt2.docx
Hi, Thanks you for your reponse. After change this parameter, now all is Ok after testing. Thank you very much.