It works! Thanks very much
He has rights to do it. Is there specific paramater for manual planing?
Ok, so I keep it set "yes". Into Global Parameter / Activity, there is "Manual Planned Interventions enter work as" : "planned" or "real". What does ...
I see "alimentation automatique du réél" in "oui". Does it mean it put work planned asa we calculate the planning?
We may ask you for a custo 🙂 Best regards,
Thanks very much! Have a nice day
I solved my issue by marking activities out of the planning calculation.
It calculated by modifying original start dates with new ones following "next to the other activities end" of the WBS. I need it plans with the or...