Reply
Ability to link a ticket to a document with a version.

Bonjour, The objective is to be able to know the number of tickets ( or NCs) that was raised for a version of a document in order , as an exemple, ...

9 years ago
Topic
Topic
Replies: 1
Views: 3460
Reply
[SOLVED] S curve Planned value not egual to project estimates

Hello Babynus, Have you had the time to investigate the problem? I have added notes to my discussion on the forum and I am not shure you have receiv...

9 years ago
Reply
View Baselines bars ( références)

Hi I have deactivated all extensions in Chrome and I have tried several zoom factors and I can not see the baselines bars. Do you have any other s...

9 years ago
Reply
View Baselines bars ( références)

I noticed that I can see the baseline bars if I use Firefox but I can not see them with Chrome!

9 years ago
Topic
Replies: 4
Views: 5714
Reply
[SOLVED] S curve Planned value not egual to project estimates

To complement the issue, the hours on burn down chart seem to be correct. Regards Michel

9 years ago
Reply
[SOLVED] S curve Planned value not egual to project estimates

Hello, It does not seem to be a conversion issue since 207 assigned hours represents 25.8 days of effort ( at 8 hours per day) and the S curve displa...

9 years ago
Topic
Replies: 1
Views: 2521
Reply
[SOLVED] work assignment

Hello, I have assigned a ressource testeu1 to the project la banque du Québec and i have affected the ressource to the project see sreen shot teste...

10 years ago
Reply
[SOLVED] work assignment

Thank-you for your fast reply, The ressource is asssigned to a task (see file testeur 2) but under «planification par ressource» , there is no data ...

10 years ago