I checked this feature, and confirmed that it works fine. However, during the testing, I noticed that tasks for a resource were overlapping. This w...
Yes, that was my point: The first three mandatory fields should be sufficient. Once the user enters something in these fields, ProjeQtor should ...
There are different possibilities: 1. The resource is already allocated 100% to one project, and I try to allocate him to another project in the sa...
Yes, you are right! Actually I don't need to look at the Timesheet: My own screenshot (the right-click on the task in the Planning view) shows that...
I will test this again, and revert. @check box being active only when visible: I am sorry, but I did not understand this caution. I was on the sa...
Well, all the tasks touching the left are at the start of the project (they are in ASAP mode). But the MCP should be shown throughout the project, in...
Yes, I do understand the problem! 🙂