Last seen: 27 Oct AM 11:1010
c[v6.0.3 acceptance review] - OK . Ticket fixed. Thanks you. Projection is done as a real and usefull 45° curve.
[v6.0.3 acceptance review] : ticket is now OK. For each modification of milestone date, the 45° curve is automaticly upadated. Thanks.
[Acceptance review 6.0.3] : NOT OK. This issue is not fix. Some indications in the legend are not visible. You can find attached, this problem corespo...
[Acceptance review 6.0.3] : Ok . Now is possible to fix a planning in the past. You're right, is not a 45°curve issue but a baseline configuration iss...
We confirm this issue. some internal users have this refresh page....
A "refresh page" appears when i tried to refold a project ...
I think not understand the mecanism ....(maybe too late) 😉 i dont understand.the term "adminitratives projects" could you precise the mecanism....
With the "planning gantt " report in "planning" (report view) on chrome , there is also the issue
I use firefox Attached the message... I don't have the issue with chrome....even there is the possibility to export with specific mode "porrtait...
It is a random bug. when we try to insert our real allocation, there is a page refresh....
Exactly, it is the main principle of 45° project management curve. Curve and bijective curve must be go to the end of the last milestone