[SOLVED] summary of availability rapport negative or null for pool

3 Posts
2 Users
0 Reactions
2,073 Views
(@pipobru)
Posts: 180
Active Member
Topic starter
 
[#6113]

Hello,
with the las t version (8.1.0) for pool of ressources, availability are null without affection (no charge) and negative if a charge are planned. See scren in attachement. may be the bug #4035 is not fuly efficient ?


 
Posted : 09 Jul 2019 14H10
(@babynus)
Posts: 14952
Member Admin
 

It is normal.
It is to have correct SUM for each column (month).

Availability of Pool is already counted as availability of resources in the pool.
So all planned work on pool is something that will decrease availability of resources (but we don't klnow wich, it can be any of the resources of the pool).


 
Posted : 09 Jul 2019 14H19
(@pipobru)
Posts: 180
Active Member
Topic starter
 

Ok, I understand


 
Posted : 09 Jul 2019 14H23