[SOLVED] work assignment

You must assign work to resource in the "Assignation" section. To see, planning in the Gantt view you must build the planning. Click on t...

10 years ago
Topic
Replies: 1
Views: 2641
Reply
[SOLVED] Accidentally closed activity

When you create an activity, you selected an activity type. This activity type is linked to a workflow. A workflow defines the possibility to ...

10 years ago
Reply
Store technical informations about projects

Put technical information in product element. With product version will be able to link the project with product.

10 years ago
Reply
Question with times

Information available in manual:

10 years ago
Reply
Milestone and diary

Use a meeting. A meeting is like a fixed milestone. If you want like a floating milestone, you use an activity with planning mode "Work together...

10 years ago
Reply
Don't share the ressource

You could improve the team feature. A team could contain project managers and resources. A resource could be shared among several teams. ...

10 years ago
Reply
Is that api for projeqtor exists?

You can't use "Postman" or anything else. You must encrypt your data. But, PHP function "AesCtr" must be executed into the PHP environment. Copy an...

10 years ago
Reply
How to preview a document in projeqtor (eg a PDF)?

Document viewer available for image files and PDF. Click on icon.

10 years ago
Reply
Ticket managment ambiguity

Ticket management is used mainly to interact with customers. (Customer Development team). Is exact? Tickets have a mandatory relationship with ...

10 years ago
Topic
Replies: 4
Views: 3068
Reply
Successors

Is it possible in future version adds a checkbox in the dialog box, allowing display all values from visible projects? To avoid to select "All pro...

10 years ago
Reply
Successors

- eithe using the "magnify" button to search for element in list that includes items from all project - manually "draw" the dependency in the Gantt p...

10 years ago
Topic
Replies: 1
Views: 2644
Reply
[SOLVED] problem when we create activities, milestones and tickets

This is not a bug. 🙂 Check activity type named "Task". The parameter "result mandatory on done status" is checked. When you pass to "Done" st...

10 years ago
Reply
trigger on workflow

You can change the automatically status on activity. See explanation below. Available in version 5.2 or 5.3.

10 years ago
Reply
Sponsor

Sponsor come from the contacts list.

10 years ago
Reply
Resource Planning Issue with Projeqtor 5.3.3

Do you have "Administrative projects" or "Operational projects". Only operational projects appear in Gantt view.

10 years ago
Reply
[SOLVED] Issue with automatic assignment of all ressources on activities

This is not a bug, but a normal behavior to an "Administrative project". See project type description below. For example, user "admin"...

10 years ago
Reply
[SOLVED] E-mail notification problem

So, the problem don't come from ProjeQtOr ! Contact your email servers administrator.

10 years ago
Reply
[SOLVED] Overall progress?

No more left work, but the task status will not change because at issue is occurring I do not understand. Can explain in more detail? Check your a...

10 years ago
Reply
[SOLVED] Responsible?

First things first! Why others users must enter a result? Explain to me, what do you want the software to do for you.

10 years ago
Reply
[SOLVED] Responsible?

Sees the responsible like a person that ensure execution of works. For instance, you can define a responsible to a delivery. A responsible receives...

10 years ago
Reply
error report

Check if the "report" directory exist. Check if your web server user has access to write on directory.

10 years ago
Reply
[SOLVED] E-mail notification problem

Check error message in log file and send it.

10 years ago