You must assign work to resource in the "Assignation" section. To see, planning in the Gantt view you must build the planning. Click on t...
When you create an activity, you selected an activity type. This activity type is linked to a workflow. A workflow defines the possibility to ...
Put technical information in product element. With product version will be able to link the project with product.
Information available in manual:
Use a meeting. A meeting is like a fixed milestone. If you want like a floating milestone, you use an activity with planning mode "Work together...
You could improve the team feature. A team could contain project managers and resources. A resource could be shared among several teams. ...
You can't use "Postman" or anything else. You must encrypt your data. But, PHP function "AesCtr" must be executed into the PHP environment. Copy an...
Document viewer available for image files and PDF. Click on icon.
Ticket management is used mainly to interact with customers. (Customer Development team). Is exact? Tickets have a mandatory relationship with ...
Is it possible in future version adds a checkbox in the dialog box, allowing display all values from visible projects? To avoid to select "All pro...
- eithe using the "magnify" button to search for element in list that includes items from all project - manually "draw" the dependency in the Gantt p...
This is not a bug. 🙂 Check activity type named "Task". The parameter "result mandatory on done status" is checked. When you pass to "Done" st...
You can change the automatically status on activity. See explanation below. Available in version 5.2 or 5.3.
Sponsor come from the contacts list.
Do you have "Administrative projects" or "Operational projects". Only operational projects appear in Gantt view.
This is not a bug, but a normal behavior to an "Administrative project". See project type description below. For example, user "admin"...
So, the problem don't come from ProjeQtOr ! Contact your email servers administrator.
No more left work, but the task status will not change because at issue is occurring I do not understand. Can explain in more detail? Check your a...
First things first! Why others users must enter a result? Explain to me, what do you want the software to do for you.
Sees the responsible like a person that ensure execution of works. For instance, you can define a responsible to a delivery. A responsible receives...
Check if the "report" directory exist. Check if your web server user has access to write on directory.
Check error message in log file and send it.