You should, data could be refreshed.
HI, Have you thought to replan the planning ?
Hello, Please check on project screen if this project is not fixed or paused. ( a cell ticked on it) Otherwise, please give some more informations...
Good to know, Soon we will create a new alert when the predecessor wil ovestep the sucessor. As a meeting is settled once for all, decision to cha...
if i have well understood your question, i think so ! Lets' test it !
hi, it is posible to link a meeting to the end of an or severals activities with dependencies. On gantt it is visible On boards of dependencies bot...
Hello Global parmeters / WORK TIME / UNITS FOR WORK
HI, Sorry, no idea. it depends only on your habits, the way you work. Just an information, the workflow can progress without workload, it is just ...
Hi, To avoid misunderstanding, we should have written : calculation ( or recalculation ) of the left workload from this date. All left work over al...
HI, Yes Projeqtor is magic 😉 see below and go to it
You are welcome ! You can impact the planning by playing with the different planning modes.respecting constraints you gave. In your case : you ca...
if A) Only data written on valided : It keeps that to start to planify : so : expected ( valided) = planified = nice draws = nice Gantt = No forecas...
Hello, I cannot answer to you with so little information cause I do not understand what you are doing. But remember : Projeqtor is not a tool to d...
Hello Left work is always recalculated from the date you recalculate your planning. It seems so logical. FYI : BLACK NUMBER IN A WHITE CELL: impute...
hi On global parameter / Planning / 2nd line "show resource on Gantt" fill the field with your choice.