Hello, Into global parameters, section imputation, you can choose to hide the line about pool from each timesheeetl. So the resource does not get...
HI Global parameter / automation / generation of alerts
Hi Do not worry, the assignments will be changed automatically without having to change them manually. Please note that on project screen you will ...
HI, You can link a contact to a supplier and define if he is a resource and or an user from this supplier.
hi Yes you can. a "task" could be an activity or something else able to be planified. bye
Hi, Go to global parameters and set up days off or worked by week into the first tab. We do not set different days of the week being planified by re...
Hi, Be careful. Template report allows to give the format you want for your reports printed or "pdfed", You can NOT create personnal report with th...
Yes screen "today" is made for that.! You can add on it reports. You can also raise alerts on types of activities for each resource who is assigned ...
HI What do you mean by Links, where ? which screen ? Thanks
Hi Easy : You just have to agree on the color of each activity that respond to an anomaly. Possibility to change the color of an activity on the G...
Yes it is weird. Investigating...
Hi Thank you to use Projeqtor. It will be great for you. i think you have to spend some time to read the friendly manual pressing f1 or following t...
Hi i add some informations: YES: You can use the rate on allocution on project and dedicated periods on project when you trig the dedicated pop up m...
Hi You can refer and or link a milestone from a project to another one ONLY if you have visibility and right on BOTH
the resource is she still allocuted to this project.? i think so ! But please check her FTE ( If=0 behaviours are blocked)
Ok thanks, still investigating. Project or activity is not fixed. No real work, no special mode of planification, recalculation ok, no error with m...
i m only interested by pic of activity with id 3653 . thank you
Is there some real work entered into the succesor ? Is the sucessor is planified with a special mode as regular beetween to dates or planified interv...
OK, Gonna try to reproduce and find the solution !
Hi, Have you replanned the project ? if not, do it. Same behaviour ?
hi On ticket : treatment : use planning activity . ticket(s)will be linked to this activity Very simple.
Hello, i do not really understand your problem. You can follow and indicate real workload from ticket whatever it is linked or not to a dedicated a...
Yes of course your resource can not be planned everywhere on all activities per day at the same time. Be careful ! The rate you talk about do not r...
Hi, It seems that the report you are talking about displays only done work ( real work indicated on time sheet) and not planificated work.