The resource is unable to update the Actual work allocation (form grayed out)

The actual work-assignment is shown in the attached screenshot.

9 years ago
Reply
ProjeQtor fails to import Activity data (as Excel or as CSV)

I resolved the issue through trial-and-error, and found that this process is complicated, but does not have adequate help text. I have prepared a h...

9 years ago
Topic
Replies: 1
Views: 2847
Topic
Replies: 1
Views: 2573
Reply
How to specify "for the duration of this activity"?

...and then you will remember Occam's razor principle and not extend the ProjeQtor to make coffee, either! 😀

9 years ago
Reply
Problems in Real Work Allocation GUI

Issue#1 I think the words logging or recording are much better! We can even think of accounting. (In the sense of giving an account of how many hou...

9 years ago
Reply
How does ProjeQtor allow PM to control Reassessed work?

When dealing with the ticket, please also keep in mind the effect on others if there are multiple resources on the job. Some of these may not be af...

9 years ago
Reply
How does ProjeQtor allow PM to control Reassessed work?

I really am enjoying these exchange of views! You rightly quoted Hofstadler's law. It means that even the resource himself will initially feel that...

9 years ago
Reply
How to specify "for the duration of this activity"?

I do understand that, but when the task is split among multiple resources, any delay/extension of the task would require re-planning for all those res...

9 years ago
Reply
When there is no work in the week, the summary line should not show green cells.

Yes, of course I had guessed that already, but that's not a good logic, because green is NOT used to denote OK condition in ProjeQtor: It is specifica...

9 years ago
Reply
When we auto-un the plan, how to include tickets with the project activities?

I agree this is a fair arrangement. Thank you for devoting time in patiently explaining the process. It would be good to have this captured somewh...

9 years ago
Reply
When we auto-un the plan, how to include tickets with the project activities?

No the human interaction is expected to happen as a routine. 🙂 That's not my point of concern. Since the ticket is not competing with his project...

9 years ago
Topic
Reply
How to specify "for the duration of this activity"?

No, perhaps my question was not clear. We have already assigned the second resource at (say) 10%. But because we specify the effort hours for each ...

9 years ago
Reply
How to split and pause (halt) a project till further notice?

I tried this, and it did not work! The Gantt chart remains unchanged (see screenshot). In any case, this solution is not so intuitive 1. The fix p...

9 years ago