Send the ProjeQtOr log. Under .. projeqtorfileslog
The planned cost is calculated with the current daily cost (The last). Planned cost is an estimate cost. The real cost is calculated with the dail...
It's normal behavior of project type: "Administrative". For this kind of a project everybody can put real work on tasks. An assignation is automati...
The user guide is currently being completely redrafted. Can you explain to me with examples, what you want.
Me too, I don't know why. Maybe a bug. 🙁 Babynus help !
The are three ways to define planned dates. 1 - Request dates (just on right of planned dates) - Used as wish dates before the project start...
I tried your case on the test site. So, I can change the planning mode and work distribution change too. Have you recalculate the planning?
Planning calculator will distribute your 8 days (planned work) on 63 days (duration). It look like the example for "Regular in full days". So, ...
For the regular planning mode, you must set the validated duration (start and end dates). Second, you define the planned work (assigned work). In yo...
I send to you a part of the user guide that will be available in version 5.2.3. I hope this is can help you. ProjeQtOrUserGuide.pdf
Start again from the beginning. What is it this "activity menu" for you? Can you send a screen shot.
Tasks are displayed on a diary for a resource. So, if you are not specifying a resource to a task, it's normal that doesn't appear on any diary. If ...
I am not an expert, but I think TLS use another port. Port : 465
ProjeQtOr have an API (REST web service). The detail is not available in the new user guide. So they are available in the old user guide. In an att...
It's my fault! I rewrite the user guide. Next version will contain this information.
Are you executing the process to calculate planning? The process can be started in the Gantt chart.
Simple user can use "Real work allocation" screen. The column "Left" allows to change the left work for each task.
Yes, planned dates are defined according to assigned work defined for resources to tasks. For the first draft of project plan, you can use validated ...
Planned dates are defined according to assigned work defined for resources to tasks. If none assigned work is defined, then validated dates or requ...
The member must create its own individual expense. By default, a project member (profile) have visibility on own element created.
User can enter daily travel expense in "Individual Expense" screen. User can create one individual expense by month and write daily cost in expense ...
First, you must understand the concept of data visibility. Profile defined in user level allows to grant, if user has access to all projects or only ...
I will you offer a scoop on future version of the document. Internalalert.pdf
The validated work allows to define the scheduled work. The Scheduled work allows to calculate the margin (work). Consolidation of validated work ...
Administrative project is available for all resources without having to be affected. Check this!