Message erreur première connexion

Send the ProjeQtOr log. Under .. projeqtorfileslog

10 years ago
Reply
How is calculated the assigned cost for a resource?

The planned cost is calculated with the current daily cost (The last). Planned cost is an estimate cost. The real cost is calculated with the dail...

10 years ago
Reply
[SOLVED] Activity does not repect the assignment

It's normal behavior of project type: "Administrative". For this kind of a project everybody can put real work on tasks. An assignation is automati...

10 years ago
Reply
The manual user exist other, for users like making processes manage a project??

The user guide is currently being completely redrafted. Can you explain to me with examples, what you want.

10 years ago
Reply
Regular in full days plans partial days

Me too, I don't know why. Maybe a bug. 🙁 Babynus help !

10 years ago
Reply
How is filled the field planned start date in menu activity

The are three ways to define planned dates. 1 - Request dates (just on right of planned dates) - Used as wish dates before the project start...

10 years ago
Reply
Regular in full days plans partial days

I tried your case on the test site. So, I can change the planning mode and work distribution change too. Have you recalculate the planning?

10 years ago
Reply
Regular in full days plans partial days

Planning calculator will distribute your 8 days (planned work) on 63 days (duration). It look like the example for "Regular in full days". So, ...

10 years ago
Reply
Regular in full days plans partial days

For the regular planning mode, you must set the validated duration (start and end dates). Second, you define the planned work (assigned work). In yo...

10 years ago
Reply
Regular in full days plans partial days

I send to you a part of the user guide that will be available in version 5.2.3. I hope this is can help you. ProjeQtOrUserGuide.pdf

10 years ago
Reply
How is filled the field planned start date in menu activity

Start again from the beginning. What is it this "activity menu" for you? Can you send a screen shot.

10 years ago
Reply
Fixed duration

Tasks are displayed on a diary for a resource. So, if you are not specifying a resource to a task, it's normal that doesn't appear on any diary. If ...

10 years ago
Reply
[SOLVED] Mail SMTP Configuration - Status wait

I am not an expert, but I think TLS use another port. Port : 465

10 years ago
Reply
Is that api for projeqtor exists?

ProjeQtOr have an API (REST web service). The detail is not available in the new user guide. So they are available in the old user guide. In an att...

10 years ago
Reply
How to put a planned date on an activity

It's my fault! I rewrite the user guide. Next version will contain this information.

10 years ago
Reply
How to put a planned date on an activity

Are you executing the process to calculate planning? The process can be started in the Gantt chart.

10 years ago
Reply
How to fill “days left” for a user?

Simple user can use "Real work allocation" screen. The column "Left" allows to change the left work for each task.

10 years ago
Reply
How to put a planned date on an activity

Yes, planned dates are defined according to assigned work defined for resources to tasks. For the first draft of project plan, you can use validated ...

10 years ago
Reply
How is filled the field planned start date in menu activity

Planned dates are defined according to assigned work defined for resources to tasks. If none assigned work is defined, then validated dates or requ...

10 years ago
Reply
imputation and expense

The member must create its own individual expense. By default, a project member (profile) have visibility on own element created.

10 years ago
Reply
imputation and expense

User can enter daily travel expense in "Individual Expense" screen. User can create one individual expense by month and write daily cost in expense ...

10 years ago
Reply
1st test wave

First, you must understand the concept of data visibility. Profile defined in user level allows to grant, if user has access to all projects or only ...

10 years ago
Reply
How to use "Alert" ?

I will you offer a scoop on future version of the document. Internalalert.pdf

10 years ago
Reply
consolidation travail validé

The validated work allows to define the scheduled work. The Scheduled work allows to calculate the margin (work). Consolidation of validated work ...

10 years ago
Reply
1st test wave

Administrative project is available for all resources without having to be affected. Check this!

10 years ago