[SOLVED] How to change project planned end date

:(, that'll be a hell of work. I think I understand more how it works now. 🙂

Il y a 7 ans
Répondre
[SOLVED] How to change project planned end date

I realized that I have misunderstood the project rate and the activity assignment rate for a resource. I changed some of them and now it looks much be...

Il y a 7 ans
Répondre
[SOLVED] How to change project planned end date

Ah, I see... Actually, the activity is ok now, I don't know what I have done. But the same problem occurs for other activities as well.

Il y a 7 ans
Répondre
[SOLVED] Project ordered alphabetically in Planning report

OK, in my case, the result is the same as ordered by ID. I didn't realize that I can reorder it in the planning Gantt view... Thanks!

Il y a 7 ans
Répondre
[SOLVED] How to change project planned end date

Sorry, I still don't get it. You want to see detailed planned work. I only filled in the validated start dated and end date which I have framed with t...

Il y a 7 ans
Répondre
Il y a 7 ans
Répondre
[SOLVED] How to change number of hours per day

That's exactly what I meant. So I can only set it to 7 hours per day to make the plan more reasonably, do you agree? I see that the feature is plan...

Il y a 7 ans
Répondre
Sujet
Répondre
Répondre
[SOLVED] How to change number of hours per day

Thanks! It's working now. The reason I'm changing it is that we have some hours that we don't work on projects each week so the actual working hour...

Il y a 7 ans
Sujet
Replies: 7
Views: 6761
Répondre
[SOLVED] How to change project planned end date

I got another problem as shown in the screenshot that the second activity should be planned for April whole month with a fixed duration, however, it p...

Il y a 7 ans