Hello We're going to need a little more information so that we can give you the beginning of an answer. There are about forty fields on the ticket...
Hello any additional information would not be a luxury. A screenshot of your assignments? of your planning, planning by resource, Timesheet... some...
Hello We do not reproduce. What version are you working on?
Hi, tickets are not plannable and will therefore not be visible or interpreted on a gantt chart. (Except on the global planning view as regards Pro...
Indeed, you're right, we have a problem. ticket 9271 recorded. We are investigating.
You need to allow your team member to use the resource filter on reports.
This message appears because you are trying to take one or more days of leave on days that you have already taken. For example: Today is December ...
the problem is known and will be fixed very soon, the ticket is registered at #9258. These logs, generated every 10s, just indicate that your mailbox...
Have you looked at the resource planning screen? You can view resources in the same project and sort them by resource, team and/or organization.
Except in the admin screen to close the application or close a user, we do not offer any account blocking functionality. As you pointed out, it is ge...
As Project leader is not able to see the individual's work hours for the resources who are in his projects it seems to me that this is exactly what t...
Hello Periodics meetings are not dynamic. If the project extends in time after creating the meetings then the dates of the recurring meeting will ...
In some of the earlier versions, ... Our versions are on an incremental development, if it was present once, we do not remove it and it will be prese...
Hello ! Have you tried using the multiple update tool on the assignments screen?
hello Closing items, no matter the item, even projects, does not purge any work data. By closing, you archive. The data continues to be readable an...