Reply
SQLSTATE[42000]: Syntax error or access violation: 1044 Access denied for user

Please note that DB in not expected to exist. So convertion to lowercase is done to enforce compatibility (including with postgresql)

3 years ago
Reply
pools are lacking in the resource list of work plan per resource and per week

I would prefer that pools be redistributed in real resources It is possible only if you select "Unique resource" in assignment for pools. Then you g...

3 years ago
Reply
Improve workload reports to help identify under workloads

In fact it does, for users able to manage these projects (admin for instance.

3 years ago
Reply
diary view

On Agenda, Responsible sees Activity at the Target date. Assigned resource see the Activity at each planned date

3 years ago
Reply
KPI

Hi, I don't agree Adding this functionality to the next ProjeQtOr update would make the software even more polyvalent for the whole community I t...

3 years ago
Reply
Copy an activity as an action

It is also possible if you open detail in planning view. Copy an activity into an action works fine. It seems that copy with right click contextua...

3 years ago
Reply
Copy an activity as an action

This feature already exists.

3 years ago
Reply
Problème clôture d'activité

I would at least give 1 advise to mariem.baccar : just read the message. If you don't understand the meaning of the message, I'm afraid we cannot do...

3 years ago
Reply
How to export / import & replace assigments?

Just export assignments with IDs. Change data then reimport files with preserved IDs, assignments will be overwritten. Note that some fields that ar...

3 years ago
Reply
[SOLVED] leave period & strange message in coherence control

Hi, Issue logged will be fixed in next patch. Strange as we never faced this issue (may occur for planning element that has no WBS) Possibly ch...

3 years ago
Reply
KPI

As an addition, your KPI are not (IMO) related to Project Management. For instance we will never manage the gender of resources are this as no relati...

3 years ago
Reply
[RESOLVE] Error update 11,1,2 -> 11.1.3

Hi, This will be fixed. To fix your instance, please executeALTER TABLE `qtor_reportlayout` CHANGE `idFilterCriteria` `idFilter` INT UNSIGNED NULL D...

3 years ago
Reply
Import of milestones impossible : need ValidatedDuration (doesn't exist for)

I think it is the planning mode which is not correctly set, possibly not fitting a milestone planning mode. Best is to export an existing milstone ...

3 years ago
Reply
Unable to change activity planning mode

Is it possible that customing screen while cause such a behavior ? Yes, for instance if planningmode is set as readonly (globally, or for a type or f...

3 years ago
Reply
Assignments of closed activities disappear

For this case I would expect the same behaviour - either the assignments are shown or they are not shown. Please carefully read my answer...

3 years ago
Reply
Leaves calendar shows unknown even it is accepted

Ticket #7911 record. We'll have a look.

3 years ago
Reply
Project Email

You mean you expect to read thje emails (from IMAP mailbox) and store them on the project ?

3 years ago
Reply
Assignments of closed activities disappear

What version are you using ? Issue is that you should see a "show closed" button. When Activity is closed, its assignmments are also closed. L...

3 years ago
Reply
Unable to change activity planning mode

NB : you cannot change planning mode for Parent activities (activity that has sub-activities) Possibly you are in that case, even if sub-activities a...

3 years ago
Reply
Tickets created by input mailbox get initial state "Copied"

It seems there is an issue. We create on status "copied" to store followed before moving to status recorded. But if option 'add recipient to followe...

3 years ago
Reply
Unable to change activity planning mode

Are you sure that you connect with user having the correct profile ? Pay attention that your user may have a specific profile from allocation to proj...

3 years ago
Reply
[SOLVED] Strange Behaviour on Planning Calculation

The planning mode will generate some priorities that are more important than priority. For instance, fix duration tasks are planned before Asap. M...

3 years ago
Reply
Gantt remains blank when more than the limit should be loaded.

Hi, I think you reack the limits of the browser capacity. We set a limit to display items, defaut is 2000 and you should not increase this limit to ...

3 years ago
Reply
[SOLVED] Defaut State for meeting

All items are recorded in the "first" status, that is common to all items and should be the start of all workflows. The "first" status is the one wit...

3 years ago
Reply
ToDo lists not copied when project is copied

I would be happy if this could be implemented a little earlier Easy : you may just sponsor this evolution, you'll get it in next version. Just conta...

3 years ago
Page 32 / 599