Last seen: 30 Jun 2020 16H26
OK, in my case, the result is the same as ordered by ID. I didn't realize that I can reorder it in the planning Gantt view... Thanks!
Sorry, I still don't get it. You want to see detailed planned work. I only filled in the validated start dated and end date which I have framed with t...
Well, then I have to wait...:(
That's exactly what I meant. So I can only set it to 7 hours per day to make the plan more reasonably, do you agree? I see that the feature is plan...
Which task bar?
Yes, I did.
Thanks! It's working now. The reason I'm changing it is that we have some hours that we don't work on projects each week so the actual working hour...
I got another problem as shown in the screenshot that the second activity should be planned for April whole month with a fixed duration, however, it p...
Thank you very much Bernie! I'll see if I can get some images with english as well!
Thanks! I know that's why it is red but I don't know how it is calculated, why it is planned after the validated end date. When I calculate myself it ...
Thanks! I must be blind!!! :blink: :S You guys are awesome!!
Hi, I did the recalculate planning. I don't understand why it became red for the first activity. The rate is 57% of 80 hours work is about 18 days,...
Thanks! I have created the resource and allocated resources to their projects. I have also assigned the resource to activity, but I don't get how to ...
Hi Zoe, That's fantastic! Thank you very much! I don't know any French but I hope google translate should do the work. I created a google docand we...
I added the planned work in the validated field in Cost and works. And now it shows the correct planned date. Is it the correct place? However, it is...
Hi Zoe, How is it going with the guide? It would be really appreciated if you can share it. Thanks!
I have created activities and assigned to the project and also added time to the assigned resource if that is what you mean by assigned work. I'm v...
Thank you very much for the prompt response! I figured out the place to choose the project and now I have changed the global parameters. Everything ...