Hi. This is the Workperiod table
Hi If the admin is filling out a standard user's timesheet, there is no submit button. No actually. It's normal. Only users themselves can submit...
Hi, we have no display problem on our side. Are you sure you are not on the project portfolio view? Which version of projeQtOr? Do you have any e...
Fill the real work on the ticket screen. If you enter it in the real field, the time will be charged for you (user who enters) and on the current date...
Hello I'm not sure I fully understand what you want to do. However, we can manage LDAP and an SSO connection system if you have one
Hello Other than changing the status of the activities you want to show in the report, it's not possible. Otherwise you can get a view of the Gant...
I configured the profiles this way... And it's the way to fix them that's wrong. We have reproduced on several bases and everything is correct. Th...
Hi If you set his FTE to 0.5 then planning will always be capped at 0.5 per day on any project and any activity. If you assign an allocation rat...
Hi "I have modified Albert's default's profile with "reader" and not "Project Leader". You are confusing Profiles and access mode. The project l...
I am sorry but no... It is impossible I've tested everything possible and unimaginable, both on 10.1 and 10.2 with an all single reader profile i cre...
Upgraded to 10.2 Do not hesitate to consult the roadmap of ProjeQtOr to have this kind of information
Are you allocated to the projects ? ProjeQtOr works with profiles to distribute the rights on each project, if you are not on it then no visibility. ...
Good morning ! What version of ProjeQTOr are you on? Have these directories been copied? Did you create them after the ones that should work? What ...
Hi ! The resource is planned according to its FTE and its calendar taking into account its availability. Added to this is the allocation rate whic...
Hello there have been changes to the management of rights to documents and document directories in 9.3. Without further information, your settings...
Hello not all reports are available with an excel export. You will find the list of reports on the manual. Those exportable in excel are indicated.
Hi ! We were looking for the error without result... we thought that ProjeQtOr was too perfect to bug on it !
Hello ! Read the manual carefully. And try to plan a resource pool. You will see it works very well!
Hello, We have no errors on the use of absences on our side. What system are you using exactly. Because the absence and imputations module does...
Hello, so, if you have a parameter with a + then you will necessarily see the projects. For example, if you are manager + on actions, then you nee...
Hello you are on the resource screen. The password is in the User screen !
Ticket recorded #6751
We do not reproduce. Can you attach more item. Screenshots, error messages? browser console, projector logs?
Hello What are we talking about exactly? Attached files on item screens or attachments you can attach to emails? Because there are two very distinc...