I have got the solution by checking in automation tab in global parameter. Thanks for your continuous support.
Thanks for reply. I think you can help me through check following ERROR lines in ProjeQtOr log file. 2022-05-05 10:40:26.544 ***** ERROR ***** [V9...
Sorry Friend, But If you add assigned first & then input real, it will work fine for pending as per expected! I can't understand how you are ac...
Please find the attachment for use case in detail, step by step. projeQtOr-lefthours.pdf
Thanks, I know that duration is calculated using open day only & I am reaching near to solution but here in our Company it is only second and four...
No, I was just observing progress %, planned work, left work, assigned work & I confused about duration column.
Thanks for the reply. But it is already showing the "search" & "+" sign if I log in with administrator rights! and even I can't get that drop-dow...
Hi Expert, I need to get records of planned resources for status in (in progress, assigned) and assigned work<=0. As per my understanding, I hav...
I would like to know how the warning threshold "04/08/2022" is showing?!
Thanks a lot for giving a great understanding of filtering.
Thank you So much, It worked. I will change my practice.
I am already doing so, but it is not showing wbs in help!. Please find attachment for reference.
Import data is showing these many fields (as per attached screenshot) , where else you are asking to import data ?! (i.e. I have CSV file with id &...
Thanks for reply. I have tried as you suggested but it is not showing any wbs in that list. Please find attachment for reference.
Thank you for reply. I tried as you instructed , but I didn't find any option to re-import those two fields ! I have checked import data , but it g...