Forum

Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.

Arkhanje
@marylene
Admin
Contributor
Joined: 03 Sep 2023 23H53
Last seen: 13 Oct 2026 18H08
Topics: 0 / Replies: 592
Reply
V12.0.1 - Filter "show closed" not saved any more?

Hello, Just in case, have you checked that you are not in archive mode in the project selector settings in the "other" tab? Otherwise can you atta...

2 years ago
Reply
Project memeber create and self-assign activity

Hello you just need to modify the rights on of the team member profile (or create a new one) put a manager role on the activities and assignments i...

2 years ago
Reply
Project creation

....???? Why .......i don't know !!!!!!! with log, capture, with more info... maybe we can help you

2 years ago
Reply
Database Error

log, capture, infos... ? no repair tools but a consistency check is planned in ProjeQtOr.

2 years ago
Reply
Invisible “on pause” project

Hello no. We have not planned this option. It is not planned on the roadmap either. But you can contact us to sponsor this evolution!

2 years ago
Reply
[SOLVED] Resource in part time

Hello Unfortunately ProjeQTOr does not manage part-time from calendars. To record Wednesday afternoons of these resources as not worked, you will ...

2 years ago
Reply
Multiple update : closed status not updated for tickets

Hello Indeed, I don't remember your version anymore but after some research, it turns out that this bug has been fixed in 11.4.4. So quickly upd...

2 years ago
Reply
document and approval

ticket #9491 recorded

2 years ago
Reply
Gantt chart

Hi ! without more information, I will try to extrapolate a little... but I suppose that if you create a project in 2025 that covers 2023, it is bec...

2 years ago
Reply
Unable to close an element with left work

Hi So, it's a bit complicated indeed. Forcing the closing of elements acts in cascade. So it will close all the elements linked or dependent on t...

2 years ago
Reply
Unable to see planning

Hello, you must have created a new profile rather than copying it from another one. So there are no distributed rights on anything, so no rights o...

2 years ago
Reply
Multiple update : closed status not updated for tickets

Hello Was the result entered on ticket #2? and the others?

2 years ago
Reply
[SOLVED] Automatic assignation in activity from Kanban

Hello We do not reproduce. Try to upgrade to the latest stable version (V11.4.4) to see if your problem persists

2 years ago
Reply
Add Requester in Ticket Simple

The creator of the simple ticket automatically becomes the requester on the tickets but for this he must be registered as a contact in addition to bei...

2 years ago
Reply
[SOLVED] Issue with Project Structure Copy - Validity Dates and Duration

Hi and happy new year too ! ...because I couldn't find the "Duration" column in the filter go through the column again you must have missed them.....

2 years ago
Reply
Planned intervention - overtime - planning for a team

Hello ! It is of course possible to do this kind of planning, however you will have to use resource pools and not teams. Feel free to take a look ...

2 years ago
Reply
plan not in days but in hours

Hello ! yes, of course! Continue your visit to the online manual! You will be able to find all the answers to your questions there!

2 years ago
Reply
[SOLVED] Issue with Work Dispatch Timesheet Entry Validation

We have configured an 8-hour limit in the "Global Parameters" under the "Work Time" tab. However, this setting does not prevent users from entering mo...

2 years ago
Forum
Reply
Chronology partialy visible

We have not planned this possibility, the timeline not being the most used tool on the planning screen. But do not hesitate to ask for a quote for a ...

2 years ago
Reply
Status change on assignment doesn't work

Hello So, the global parameter "change status on assignment" is done on... drum roll! an assignment! There you inform the person responsible for an...

2 years ago
Reply
Agenda synchronisation

A quick look at the forum and the answer is here!

2 years ago
Reply
Calendar unable to add holldays

Hello I am not reproducing. Adding any date works fine on our side. Just in case, even if the "day calculated from Easter" field appears, it is ...

2 years ago
Reply
Screen customization : can't change default value for planning mode

hello no need for the custom screen to force a planning mode on your activities. Go to the activity types and indicate for each type that you have...

2 years ago
Reply
[SOLVED] Invalid login parameters on fresh install 11.4.2

Hello It seems that you have put a prefix on your tables, and the ".poc" must be problematic. Try putting a prefix without a dot and replacing it ...

2 years ago
Reply
Meeting start/end time always set to 01.00

We do not reproduce this problem. What version of ProjeQtOr are you working on? Can you attach the logs? Messages in the browser console? Have you...

2 years ago
Page 3 / 24