Hello, That's how it works! You just have to position the drop-down list on an empty space and you will have the display of all the scheduled report...
Simply click on the dispatch button to assign the work on the ticket to a specific resource or to view their work. Otherwise, it will be the resource...
Hi, Yes it is. You should take a look at the online manual of the application and read carefully the part about planning. You will find detailed i...
Hi, No, it is not possible to put several managers. However, you can add the coordinator field in addition to the responsible field. This gives...
for me only MS-Project's import plugIn is avalaible. No plugIn to import from EXCEL yes you are right, that is indeed the case, but it does not seem ...
Hello We always try to bring the maximum to our users, despite the fact that our software is completely free! We cannot integrate every request. ...
This field does not exist natively in ProjeQtOr. It is therefore a customized field that you must have created with our screen personalization plugin...
you have the list of fields available for each element when you go to the Import screen. Select the item to import and click the question mark. The im...
Hello I don't know if I understood correctly what you want to do, but in each element of ProjeQtOr you can link (linked elements) elements to each ...
thank you for using our image integration system
Hi it is a global parameter. You just need to change the setting.
Real is normally well informed have you tested on 11.1.5 if the problem persists?
Hello Effectively. We talk about the consolidation of the workload and the costs validated in the manual but it is true that we did not make it tw...
Hello Unfortunately, no one can reproduce this issue. It doesn't matter which browser or screen you create it on. What pop up are we talking abo...
Hello, to be able to use planned interventions, you must have minimum "updater" rights on the projects in authorizations > Data access (dependin...