Hello The assigned workload is automatically filled in when you assign workload in the assignments table to the resources that will work on your ac...
Please respect the forum rules. Thanks
Hello Have you checked the global parameter > Planning > Automation > consolidate validated work & cost If it is NEVER then the valid...
Hello, You can use the replacement on allocated resource on the project. Select in the allocation section the outgoing resource click on the ...
Hello You can simply use the "data import" functionality directly in the solution. Import a document version and use "importfile" to indicate th...
Currently, anyone can create / update and delete times in the dispatch pop-up for any other resource. According to your settings. First problem : a...
In Global parameters in the Display tab > Defaults values for users parameters
It looks like an encoding problem. Take a look at this topic which might answer your question
Hello It looks like you have a field that is not consistent. Did you create new fields with the screen customization plugin?
Thanks. I have done this at lenght before asking questions. indeed, we realize that it was not clearly said. Thanks to you, it's done for the next v...
According to the User Guide, @ Submit Work : "The validation system is optional and can therefore be hidden. Yes the validation system. Not the sub...
The dynamic value, when it is selected for a saved filter, will offer you a pop-up with all the values present in the list and it is when calling the ...
The resource is listed as a project member in the project profile. You have to know which profile and where exactly... In a previous post and on yo...
The rights for multiple updates are calculated on the default profile because this feature allows several elements of several projects to be updated s...
Question may be a bit silly... but is the resource that must update the meeting allocated with the correct profile on the project that contains the me...
Correct me if I'm wrong. I realize there is a difference between PROGRESS-Duration and Resource Assigned Work. absolutely If I forecast 1 day...
I'M searching the help files with no results. Press F1 from ProjeQtOr... Or go to the online manual accessible from the website here
Is there a way to force the system to accept project structures (project activities and expenses, etc.) before the current date? yes of course you ...
I would like meetings to also be hidden inside their projects when I click the minus sign. this is the basic configuration. I do not reproduce th...
"Change priority project", "Change priority others element" and "Multiple update" are rights that you must give to the desired profile from the "speci...
To plan for half a day, you can use the "Manual planning" or "regular between two dates for half a day" or "quarter of a day" planning modes. But i...
Hello, It's probably an encoding problem. You must have imported data in the wrong encoding format. Re-import the same data but in the correct form...
re-import the same data but in the correct format this time. The encoding must be in UTF8_general_ci
Hello, Manual progress is entered in the processing tab in the management section. You have a progress field that you can modify manually and this...
Do I have to ask question in English in the contact form? Do you provide support / training / assistance in French? No, services such as support o...