automaticaly fill a time-sheet ?

NO, there is no link beetween both of them. We come back to the start. There is no way to imput real work in the futur for one line with 0,1 AUTOMATI...

6 years ago
Reply
automaticaly fill a time-sheet ?

Hi, You are right, you can only plan by half day with manual planification. This parameter can be reach only from V8. 5 on global parameter : wor...

6 years ago
Reply
[SOLVED] Planification of activities

Hello, I suggest to you to read the friendly manual. In your first case, planification was able to be hopefully as validated Bur unfortunatly, co...

6 years ago
Reply
automaticaly fill a time-sheet ?

You are welcome Jeeeannnn Mouliiiinnnnn

6 years ago
Reply
automaticaly fill a time-sheet ?

Hello NO but : Just one way : Manual planification mode with the global parameter set up as "planificated manual date are workload done in the futu...

6 years ago
Reply
Closed Projects become invisible

Hello Maria, From P1 you are able to see P2, from P2 you are able to see P1( allocuted on twice) From P2 you are not able to see P1 (if you are n...

6 years ago
Reply
[8.5.3]Leave are assigned to user for no reason when he display imputation view

Hi, Beyond the surprising fact that an employee cannot see his leaves as projeqtor forbidden, also we must take into account his days off to be able ...

6 years ago
Reply
[SOLVED] Customization unit for imputation

Yes of course, a simple word to your employees on this way prevently will be sufficient

6 years ago
Reply
[SOLVED] Customization unit for imputation

Your request is recorded in our roadmap. as ticket #4835. It will be dealt with in a next version release but does not present a particular urgency fo...

6 years ago
Reply
[SOLVED] Customization unit for imputation

Hello, No there is no automatism Regards

6 years ago
Reply
Working time vs activity's responsible/pool of ressources

hi, A solution consist on going to "global parameters" then "activity" then " automation" and choose "no" at the line "auto set responsible if sing...

6 years ago
Reply
Indication for missed milestone when milestone is defined by dependency

hi, Depending on your example : yes you can do it. both of them are fixed. your activity would be planned with the mode fixed duration coinciding...

6 years ago
Reply
How can I calculate Schedule Variance and Effort Variance in the tool

hi A pool is an aggregation of unit resources to be planned as a single resource. When you allocate resources to the pool you define its capacity on ...

6 years ago
Reply
How FTE variation works?

Hi, it should be, but not necessarily with 0,5 each day ( it is a maximum allowed to be planifed on one or more activities per day) first, have y...

6 years ago
Reply
How FTE variation works?

Hello Please , post on the forum directly to make it easier for our community

6 years ago
Reply
[SOLVED] calendar with half day

Hi, Half day is not automatically possible, to get that, you have to go to "absences" screen and fill thoses days with 0,5 for the resource

6 years ago
Reply
[SOLVED] How to use Leave or Absence correctly for different days

Nothing confusing. you have just to create an administrative typed project, create one or more activies on it like day off and then select this lin...

6 years ago
Reply
[SOLVED] How to use Leave or Absence correctly for different days

Hi, First, apply the best of the calendars as close as possible to the presence for each resource. Then go to the "absences" screen and correct wh...

6 years ago
Reply
Ressource Planning

HI, Trying to understand, just wait a while please, we come back soon. thank you.

6 years ago
Reply
Ressource Planning

Hello, Everythings filled seems to be good. Have you refresh your cash browser ?

6 years ago
Reply
Ressource capacity different per day

hi, The only way to refine work per day is to use screen " absence" (or " time sheet") yes, this requires to repeat the operation every week filling...

6 years ago
Reply
[SOLVED] Pool of resources - resource in several pools at 100%

I really do understand what you are looking to do. The only way is to fill single periods on allocation for the resource on each pool. But you are ...

6 years ago
Reply
Periodic meeting

I can not reproduce, it is fine for me. Please could you stretch views attached to get more visual informations

6 years ago
Reply
[SOLVED] Pool of resources - resource in several pools at 100%

Do you assign another resources into pools ? Is she already planned on others activities ? no and no i guess.. Yes in this very simple case it is pla...

6 years ago
Reply
[SOLVED] Pool of resources - resource in several pools at 100%

HI, Do not really worry about this value ! Why ? In order to be able to plan pools due to projeqtor algorithm, we have to set up some limits. This...

6 years ago