Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
NO, there is no link beetween both of them. We come back to the start. There is no way to imput real work in the futur for one line with 0,1 AUTOMATI...
Hi, You are right, you can only plan by half day with manual planification. This parameter can be reach only from V8. 5 on global parameter : wor...
Hello, I suggest to you to read the friendly manual. In your first case, planification was able to be hopefully as validated Bur unfortunatly, co...
You are welcome Jeeeannnn Mouliiiinnnnn
Hello NO but : Just one way : Manual planification mode with the global parameter set up as "planificated manual date are workload done in the futu...
Hello Maria, From P1 you are able to see P2, from P2 you are able to see P1( allocuted on twice) From P2 you are not able to see P1 (if you are n...
Hi, Beyond the surprising fact that an employee cannot see his leaves as projeqtor forbidden, also we must take into account his days off to be able ...
Yes of course, a simple word to your employees on this way prevently will be sufficient
Your request is recorded in our roadmap. as ticket #4835. It will be dealt with in a next version release but does not present a particular urgency fo...
Hello, No there is no automatism Regards
hi, A solution consist on going to "global parameters" then "activity" then " automation" and choose "no" at the line "auto set responsible if sing...
hi, Depending on your example : yes you can do it. both of them are fixed. your activity would be planned with the mode fixed duration coinciding...
hi A pool is an aggregation of unit resources to be planned as a single resource. When you allocate resources to the pool you define its capacity on ...
Hi, it should be, but not necessarily with 0,5 each day ( it is a maximum allowed to be planifed on one or more activities per day) first, have y...
Hello Please , post on the forum directly to make it easier for our community
Hi, Half day is not automatically possible, to get that, you have to go to "absences" screen and fill thoses days with 0,5 for the resource
Nothing confusing. you have just to create an administrative typed project, create one or more activies on it like day off and then select this lin...
Hi, First, apply the best of the calendars as close as possible to the presence for each resource. Then go to the "absences" screen and correct wh...
HI, Trying to understand, just wait a while please, we come back soon. thank you.
Hello, Everythings filled seems to be good. Have you refresh your cash browser ?
hi, The only way to refine work per day is to use screen " absence" (or " time sheet") yes, this requires to repeat the operation every week filling...
I really do understand what you are looking to do. The only way is to fill single periods on allocation for the resource on each pool. But you are ...
I can not reproduce, it is fine for me. Please could you stretch views attached to get more visual informations
Do you assign another resources into pools ? Is she already planned on others activities ? no and no i guess.. Yes in this very simple case it is pla...
HI, Do not really worry about this value ! Why ? In order to be able to plan pools due to projeqtor algorithm, we have to set up some limits. This...