Hi Did you replan the project ?
Hi, Yes it is possible. GO to global parameter / WORK / UNITS FOR WORK ; Please note that 7h 8h or 9H etc is considered as 1 at the end of the da...
Hello Maria, Please be careful with the dates of displaying "from the" "until" , sometimes i hide too weeks without paying attention on it. On t...
Hello, I suggest to you if you have not ever read the contextual help, to press f1 from the screen ticket. It would be helpful. Regards
HI it is very simple. Go to " controls and automatisms" then "workflows" create or modify one of them ( see attachment) then give authorization...
hello on report / steering charts : on ticket the calculation is real work / Estimated work. if > 1 the resource is working slower than expect...
This way, you have to buy a plug in "screen customization" . you can add, delete, move, and modify a lot of fields and also the possibility to refi...
HI, On which screen or list ?
hi go to parameters then list of types then activity type then select then go to beahavior then check ou uncheck last line :"no left wor...
HI, Do not allocated them on your project. Or their projects should not be subprojects of yours. or indeed configure rights and profils once again...
HI welcome to our community. It is very simple. Please read the attachement. use a name and its password to get access
HI, You can do it. please press this buttom and then select your choices to be displayed on list area Very simple. Regards
no. it concerns only automatical planification.
please read babynus's answer
I mean, validated date (start- end) on the detail dashboard of this activity on rubric "progress"
No. It is fixed this way. On a mandatory field, the first object of the list is selected by default.
yes this workaround has its limits.
HI, Yes, The list keeps the first object on the list type or value sorted by order. Then it is bothering you , you can add an object with a "symbol"...
hI, I think you have given a validated date on this activity...,? On the contrary it is due to a technical issue on configuration email server
HI, yes of course, have a look in INDICATOR inside CONTROLS and AUTOMATISMS. You can even send programmed reports by email using the dedicaded botto...
GOOD ENJOY PROJEQTOR 🙂
HI, There is not best way. Projeqtor follows the way you want to work. You can use special mode of planification for an activity to take into accoun...
Hello, In my opinion, it seems unskilful to plan ( with simulation) only some projects because on reality those projects will impact the others on...
Hello, Matrix of skills is not yet implemented on Projeqtor. It will be set. For the moment, you can nevertheless use the feature "functions" for ea...
Have you assigned resources on activities with woarkload before ? On time sheet : Entering real work ( as planned) you are going to modify the % ...