yes of course
HI, No, but it could be an improvment...
HI WELCOME !!!!!! You can not suppress this first statu. It is one the basis into this application. Creating an element you get an ID and a first...
Projeqtor do never give one single solution. Each user use it as he wants.
hi manual planification or filing a line on timesheet screen which belongs to an administrive project type or the worst solution creating a mee...
Hello You can create an advanced filter sorting list as you explained. You can use the button on the very right side next the selector opening a p...
Hi, On this screen, red color means more or less compare to its FTE to be producted and then declared within a week.for all activities she is assi...
hello, Yes, the wording is not clear. this is the sum of customer orders and not suppliers. We are going to modify the text
No , they are not displayed on Gantt, but other projects obviously and fortunatly take into account those one.
NO 8H or 10 H is always 1 the loadwork could be planned and worked PER DAY. PLEASE SEE global parameter work time unit for work. yes you have ...
may be it's depend on wihch version number you are working with. each user can change the reference set up by the admin in "user parameters"
Hello, it is not complex, it is complete. yes, It takes a little time (and money) to invest to understand how it is powerful and usefull.
please refresh your cash on web
user parameters the fifth line
Hello? just clic the cell is a resource from user screen, or just clic is an user from the resource screen will simplify your action. they are not s...
enter some real work on a line in timesheet. leftwork will especially decrease. you can change manually this leftwork. this left work will be plan...
Status do not impact the planification and calculation. You can track each stage of your projet changing manually status depending on a single workflo...
it is donne automaticly depending on real work and left work (revisable) DONE WORKLOAD / (DONE WORKLOAD + LEFT WORK ) = REAL PROGRESS simple as AB...
hi i do not understand, you check all types but you want to exclude ( or retain) one of them ?
hi A resource is allocated by only a single calendar. whatever it is. You must create as many calendars as types of resources how they show up durin...
global parameters / activity / planning / The fourth line.
hi, then recalculated projects will take into account this fact.( with shared resources ) you can close, if you want, this project. it won't be di...
HI Go to the screen "user" and click on the dedicated feaurture on the right side of the screen
HI, Yes it is a good solution among all solutions