Activities Taking Less Than a Day

Hi Gunter, Trying to understand and solve your issue, i answer you firstly for your last question. Prirority 1 is higher than 999. It means that t...

7 years ago
Reply
Project selector

HI If profile of user has one access mode, for any screen, that give visibility to "all items of all projects", all projets lists will be full (incl...

7 years ago
Reply
[SOLVED] How to change number of hours per day

hi You have just to change per hour by per day, Then you can modifiy the number and change once again per day by per hour. Be careful, in the inter...

7 years ago
Reply
Activities Taking Less Than a Day

Hello, All you need to do is go to the global parameters and then to the work section, then into work unit to change from day to hour. Priorities ar...

7 years ago
Reply
How to change administrative project type?

Hi Administrative project are not operational project type. There is no work left to inform on them. To solve your problem, simply change the type...

7 years ago
Reply
Planning activity on half day

ello Please check it on global paramters as follow, change yes by no ( can start the same day) Regards

7 years ago
Reply
Plugin screen custom - "Elements de travail"

HI Sorry, i do not understand what is the matter. For my part, I can hide by profil each of them. Please explain with attachement.

7 years ago
Reply
Affectation inheritage

To be more clear, there is no allocation created automatically, but rights defined on parent project are automatically inherited to sub-projects.

7 years ago
Reply
Affectation inheritage

hi He is automatically allocated to all sub-projects with the choosen profil ( which can be modified on each sub-project and so on...) Regards

7 years ago
Reply
8 years ago
Reply
Project selector

HI, On the list of all projects you can use the icon "filter" to get a new list filtered by customer. Dynamic option filter allow you to choose w...

8 years ago
Reply
Overlap of activities ?

Perfect. Indeed after making changes, the automatic calculation is done automatically only if the user is on the planning screen and the box is checke...

8 years ago
Reply
Start and End date are the same

Hi, Could you send some attachments of your screens ? Thank you

8 years ago
Reply
Overlap of activities ?

HI, Overlapping is possible by specifying a negative number. However, this does not mean that planification will necessarily take this into account...

8 years ago
Reply
Automatic modification of an element's status

HI First question : yes you can . Each project is typed. On each type could depend a singular workflow. Second question : yes but only on macro sta...

8 years ago
Reply
[SOLVED] Continuous activity - do not interrupt activity with another activity

HI, You can use either - the planning mode " must not start before the validated start date" or - create a dependency beetween activities with a...

8 years ago
Reply
Hide closed project from the ressource view

Hello, If you have the right to do it, you just have to withdraw its affectation to the project. By the way, an administrator ( your case into the p...

8 years ago
Reply
[SOLVED] Missing some profiles in Affectation combobox

hi You have created a new profil and you have certainly failed to choose a sort order for this profil into this list. De facto, it is at the top of...

8 years ago
Reply
[SOLVED] lock planned work

hello, The only solution is to input real work in advance as expected. Meetings are work. Assignement on meeting adds work and never decrease the...

8 years ago
Reply
Planning dates

HI Planned : calculated by the application depending on constraints given: availabilities of resources, planning mode, left work... Valided : dates...

8 years ago
Reply
Send notification to Successor's Activity Responsable.

HI, we can not do it with "a direct automatism" but you can do it by one another way. - Go to control and automation - send email on event per ...

8 years ago
Reply
Planning calculation

HI, Tasks are always well calculated depending on constraints, availability of resources, and left work, so you can not "draw" a planning as well as...

8 years ago
Reply
Gantt Chart behaviour

Hello, On the Gantt chart, ONLY calculated dates are displayed. These calculated dates can sometimes be identical, and whatever the chosen planning...

8 years ago
Reply
Assignations to administrative projects

hi An administrative project type is tagged by the code ADM ( default configuration in on Menu parameters / types lists / projects types). On this ki...

8 years ago
Reply
[SOLVED] Change WBS of an administrative project

Hi You have just to change the type of the administrative project into a type of an operational project, then perform a drag and down to the top, and...

8 years ago