Hi Gunter, Trying to understand and solve your issue, i answer you firstly for your last question. Prirority 1 is higher than 999. It means that t...
HI If profile of user has one access mode, for any screen, that give visibility to "all items of all projects", all projets lists will be full (incl...
hi You have just to change per hour by per day, Then you can modifiy the number and change once again per day by per hour. Be careful, in the inter...
Hello, All you need to do is go to the global parameters and then to the work section, then into work unit to change from day to hour. Priorities ar...
Hi Administrative project are not operational project type. There is no work left to inform on them. To solve your problem, simply change the type...
ello Please check it on global paramters as follow, change yes by no ( can start the same day) Regards
HI Sorry, i do not understand what is the matter. For my part, I can hide by profil each of them. Please explain with attachement.
To be more clear, there is no allocation created automatically, but rights defined on parent project are automatically inherited to sub-projects.
hi He is automatically allocated to all sub-projects with the choosen profil ( which can be modified on each sub-project and so on...) Regards
HI NO.
HI, On the list of all projects you can use the icon "filter" to get a new list filtered by customer. Dynamic option filter allow you to choose w...
Perfect. Indeed after making changes, the automatic calculation is done automatically only if the user is on the planning screen and the box is checke...
Hi, Could you send some attachments of your screens ? Thank you
HI, Overlapping is possible by specifying a negative number. However, this does not mean that planification will necessarily take this into account...
HI First question : yes you can . Each project is typed. On each type could depend a singular workflow. Second question : yes but only on macro sta...
HI, You can use either - the planning mode " must not start before the validated start date" or - create a dependency beetween activities with a...
Hello, If you have the right to do it, you just have to withdraw its affectation to the project. By the way, an administrator ( your case into the p...
hi You have created a new profil and you have certainly failed to choose a sort order for this profil into this list. De facto, it is at the top of...
hello, The only solution is to input real work in advance as expected. Meetings are work. Assignement on meeting adds work and never decrease the...
HI Planned : calculated by the application depending on constraints given: availabilities of resources, planning mode, left work... Valided : dates...
HI, we can not do it with "a direct automatism" but you can do it by one another way. - Go to control and automation - send email on event per ...
HI, Tasks are always well calculated depending on constraints, availability of resources, and left work, so you can not "draw" a planning as well as...
Hello, On the Gantt chart, ONLY calculated dates are displayed. These calculated dates can sometimes be identical, and whatever the chosen planning...
hi An administrative project type is tagged by the code ADM ( default configuration in on Menu parameters / types lists / projects types). On this ki...
Hi You have just to change the type of the administrative project into a type of an operational project, then perform a drag and down to the top, and...