Leaves in worload plan

Is it normal that the project automatically created by the module (named PROJECT - HOLIDAY PERIOD) is invisible in the 'projects' section? yes, thi...

2 years ago
Reply
Activity expenses do not show up in budget detail

Hello indeed, the costs of the activities should be displayed. this is an anomaly recorded under ticket #8741 which will be corrected in the next ...

2 years ago
Reply
[SOLVED] Issue with Projects Automatically Converting to Sub-Projects on Edit

Hello the field has been made mandatory by a plugin. The screen customization. You need to go to this plugin --> Menu --> ScreenCustomization,...

2 years ago
Reply
vision of progress by the client

Hello yes, it is possible to give a "guest" profile for example for your clients users. This profile is set up by default to be a simple reader on ...

2 years ago
Reply
quick search and status filters can not be combined

my bad, I bugged the quick search... and did the tests on tags and status. So to answer your question "Is this how it should happen?"yes this is how...

2 years ago
Reply
quick search and status filters can not be combined

Hello We do not reproduce this problem. Do you have error messages in the ProjeQtOr logs or in your browser console?

2 years ago
Reply
Help Needed: Planned Days Reduced After Adding Activities

Hello, Remember that the project adapts to its content and that the calendar duration and the assigned load that will be planned have nothing to do...

2 years ago
Reply
[SOLVED] Projeqtor. Delete activity

Hello. Deletion is subject to specific rights. Check the deletion rights for the profile concerned and that the latter does not have any real work...

2 years ago
Reply
Print PDF

ticket #8653 recorded

2 years ago
Reply
set up a field (dynamic list) with the custom screen plugin

Hello you can create value lists with the plugin. I invite you to read the manual of the latter available via the store to check that it correspond...

2 years ago
Reply
Suggestion for Enhanced Admin Access to Scheduled Reports

Hello, That's how it works! You just have to position the drop-down list on an empty space and you will have the display of all the scheduled report...

2 years ago
Forum
Reply
Multi Responsible

Simply click on the dispatch button to assign the work on the ticket to a specific resource or to view their work. Otherwise, it will be the resource...

2 years ago
Reply
Copy a project, adapting the dates

Hi, Yes it is. You should take a look at the online manual of the application and read carefully the part about planning. You will find detailed i...

2 years ago
Reply
Multi Responsible

Hi, No, it is not possible to put several managers. However, you can add the coordinator field in addition to the responsible field. This gives...

2 years ago
Reply
Can a project with its activities and sub-activities be imported via Excel?

for me only MS-Project's import plugIn is avalaible. No plugIn to import from EXCEL yes you are right, that is indeed the case, but it does not seem ...

2 years ago
Reply
Modern Gantt View component

Hello We always try to bring the maximum to our users, despite the fact that our software is completely free! We cannot integrate every request. ...

2 years ago
Reply
[SOLVED] [Data import] Import documents with their linked elements

This field does not exist natively in ProjeQtOr. It is therefore a customized field that you must have created with our screen personalization plugin...

2 years ago
Reply
[SOLVED] [Data import] Import documents with their linked elements

you have the list of fields available for each element when you go to the Import screen. Select the item to import and click the question mark. The im...

2 years ago
Reply
[SOLVED] [Data import] Import documents with their linked elements

Hello I don't know if I understood correctly what you want to do, but in each element of ProjeQtOr you can link (linked elements) elements to each ...

2 years ago
Reply
Error attaching files larger than 1 MB

thank you for using our image integration system

2 years ago
Reply
[SOLVED] Tickets - Can't set responsible when it has a product assigned

Hi it is a global parameter. You just need to change the setting.

2 years ago
Reply
V11.1.4 Reel start date for activity not set

Real is normally well informed have you tested on 11.1.5 if the problem persists?

2 years ago
Reply
V11.1.5 loop when creating milestone type : infinite creation

Hello Effectively. We talk about the consolidation of the workload and the costs validated in the manual but it is true that we did not make it tw...

2 years ago
Reply
[SOLVED] V11.1.5 loop when creating milestone type : infinite creation

Hello Unfortunately, no one can reproduce this issue. It doesn't matter which browser or screen you create it on. What pop up are we talking abo...

2 years ago
Reply
Planned Interventions -access rights

Hello, to be able to use planned interventions, you must have minimum "updater" rights on the projects in authorizations > Data access (dependin...

2 years ago