You do not give any workload on this activity, you have just given a duration of 5 days; it is normal that the planning does not change. Please read t...
It is weird. Try again changing a data or clean your browser cache
HI, Just press the button which open a menu with list of projects and date to start the calculation from the left and up of the planning view scr...
Some left work could be still planified on parent activity or on others sub activities
You are welcome. No, status changes are most of the time done manually following a detailed workflow that you set up yourself on a type of the consid...
yes of course. Have you assigned workload for each resource ? Duration will be calculated depending on some planning rules, also done (time sheet) an...
Hello, It is done automatically. Did you set up workload for resource and done work ? LIke this you can calculate the progress. Have you recalcula...
Hi, You are right, when the resource is closed, into the list on dynamic filter the resource should not be displayed anymore. ticket #4453# ...
Hello, You could find an answer reading online user manual (version on V8.3 has been updated with leave system information), or contributors docume...
Hello, Please could you : - highlight the lines to be read on Gant. - SHow the resource allocations on projects and assignations on activities f...
HI You can play any test cases once added on a test session. Regards
Hello, Does the list is fully empty ? Have you tried with another indicator ? This one is it shown on the list ? Please, reset the display of th...
Hello, It could be plan after but never owe to be planed before or after. Planning calculation depend on dependencies and resources's disponibilit...
HI, Certyainly Data on this project are not sufficient allowing to calculate the burdown chart. Have you tried again giving some workload on activ...
Hello Red color shows that resource has worked more than its FTE per day. Please check for each resource their single FTP that could be let at a ...
Hello, Check the cell " fix planning " on treatment area. Regards.
HI, You can create a profil as "GUEST" or " named as you want, with clear right of simple viewing, then to be given to the Manager B allocated on A...
HI, Yes you can. -recording a baseline -Exporting data via csv -By keeping a simulation environment that suits you - By checking the box "fix pl...
Hi, Before looking for an answer to your issue, have you thought to record your operation and then recalculate the planning. I think so. Therefore, ...
You are right. A date is compulsory. Empty date should be allowed. Recorded as ticket #4233#
HI, Yes you can. use the buttom multiple update on detail area of activities screen ( icone = double floppy disks) Regards
you have just to disconnect and reconnect. Changes will be taken into account.
Do you have the right to do it ? i think so. You have just to modify the resource's profil with the new profil created on each project she is workin...
hi You allocated this resource on one or several projects with a profil allowing to create and so on, which you probably not yet changed for her. S...