Tickets automatically change status to "IDLE" when saved. (SOLVED)

Hello We're going to need a little more information so that we can give you the beginning of an answer. There are about forty fields on the ticket...

Il y a 2 ans
Répondre
the item cannot be "done" with the work left

Hello any additional information would not be a luxury. A screenshot of your assignments? of your planning, planning by resource, Timesheet... some...

Il y a 2 ans
Répondre
KANBAN : can't assign to other than me

Hello We do not reproduce. What version are you working on?

Il y a 2 ans
Répondre
Diary and teamsheet grouped by members of team or project

Hi, tickets are not plannable and will therefore not be visible or interpreted on a gantt chart. (Except on the global planning view as regards Pro...

Il y a 2 ans
Répondre
Special field ${projectCode} unvailable

Indeed, you're right, we have a problem. ticket 9271 recorded. We are investigating.

Il y a 2 ans
Répondre
[SOLVED] Granting View-Only Timesheet Access to Project Leader

You need to allow your team member to use the resource filter on reports.

Il y a 2 ans
Répondre
Error when creating new leave period

This message appears because you are trying to take one or more days of leave on days that you have already taken. For example: Today is December ...

Il y a 2 ans
Répondre
[SOLVED] Assistance Needed with Auto Ticket Creation Log Issue

the problem is known and will be fixed very soon, the ticket is registered at #9258. These logs, generated every 10s, just indicate that your mailbox...

Il y a 2 ans
Répondre
Diary and teamsheet grouped by members of team or project

Have you looked at the resource planning screen? You can view resources in the same project and sort them by resource, team and/or organization.

Il y a 2 ans
Répondre
Assistance Needed: Unexpected User Account Lockouts

Except in the admin screen to close the application or close a user, we do not offer any account blocking functionality. As you pointed out, it is ge...

Il y a 2 ans
Répondre
[SOLVED] Granting View-Only Timesheet Access to Project Leader

As Project leader is not able to see the individual's work hours for the resources who are in his projects it seems to me that this is exactly what t...

Il y a 2 ans
Répondre
Periodics meetings stops generates meetings

Hello Periodics meetings are not dynamic. If the project extends in time after creating the meetings then the dates of the recurring meeting will ...

Il y a 2 ans
Répondre
How to allocate multple activities to one resource

In some of the earlier versions, ... Our versions are on an incremental development, if it was present once, we do not remove it and it will be prese...

Il y a 2 ans
Répondre
How to allocate multple activities to one resource

Hello ! Have you tried using the multiple update tool on the assignments screen?

Il y a 2 ans
Répondre
[SOLVED] datas purge

hello Closing items, no matter the item, even projects, does not purge any work data. By closing, you archive. The data continues to be readable an...

Il y a 2 ans