Lock wait timeout exceeded error log

Hello, It seems there is lock of table, possibly deadlock. Try to restart your database.

8 years ago
Reply
[SOLVED] Bad work calculation in client orders

Hello, Thank you for your post. Indeed there is a problem. Ticket #3583 recorded.

8 years ago
Reply
What are the new features in v7.1.2?

Hello, You have to go in Product / Download / Change history. If you want to see the release note. Indeed, it is a corrective patch.

8 years ago
Reply
Problem of report when you print the bill

Hello, If you want print bill.php , you have to go directly in report -> billing -> bills. If you want print object you have to go in object...

8 years ago
Reply
resources / Function

I'm sorry ,I said something wrong. You can not delete old function if existing dependent elements. You have to manually close each old function, the...

8 years ago
Reply
resources / Function

It is possible to force delete. It is in Access right / Specific access, Section Specific update Rights, parameter "can force delete"

8 years ago
Reply
resources / Function

Hello, Indeed It is not possible to delete function if existing dependent elements. However I suggest you to close your old function.

8 years ago
Reply
Display planned hours

You can put what you want in the timesheet as long as it does not exceed the capacity of the resources. The real work can be different from the plann...

8 years ago
Reply
Display planned hours

Hello, The planned hours on the timesheet are automatically displayed in the upper left corner. In your case it is the number 8.

8 years ago
Reply
Display pbm with real work allocation

Hello, Thank you for this notice. Indeed there is a problem at the bottom alignment. Ticket #3418 created

8 years ago
Reply
Baseline

Hello, To save a baseline click on button " save a baseline of planning " then select one project and name your baseline. Once saved select your ...

8 years ago
Reply
activity display

Are you sure "Analyse du besoin" is not a parent activity of an other activity without assignment ? Can you screen your wbs columns of activities and ...

8 years ago
Reply
activity display

Hello, I think you get "Analyse du besoin" in grey because it is a parent Activity. You should look in your Activity "Spécification" and "Conception...

8 years ago
Reply
It would be very convenient if we can change the column width

Hello, Indeed you can not reduce the column width by dragging the right border for the moment. But you can change the column width If you click on...

8 years ago
Reply
Signature for emails sent through tickets

Hello, Yes, It is possible if you create email template. But today It works only with mail send automatically.

8 years ago
Reply
Hide of command "enter real as planned"

Hello, This is not possible for the moment, It is a good idea. I recorded as Ticket #3334. This evolution will have low priority in our roadmap...

8 years ago
Reply
Error sending mail for outlook mail server

Hi, Thank you for this bug reporting, we solved this problem in the last version projeqtor V7.0.4.

8 years ago
Reply
Error sending mail for outlook mail server

Hello, You should maybe check your current project and select "all projects" If you did not. Because the project filter works on screen emails sen...

8 years ago
Reply
Note

Hello, To see all the notes inserted go on ActivityStream Screen.

8 years ago
Reply
Comment faire pour voir les charges annuels de tous les projets

This report displays real work for one year for one project. When I see your real work in "Application web David Selling Price" we can see 0.06 days...

8 years ago
Reply
How to define the real work

Hello, We created an user documentation, press F1 to use it. As new user, you should read this. Many things are explained like how to use Real wo...

8 years ago
Reply
Comment faire pour voir les charges annuels de tous les projets

Hello, This report displays "Real work". Your project "Evolution travail de l'équipe IT" does not have real work. You have to enter this in scre...

8 years ago
Reply
attached files on V7.0.0

Thank you for this report : on file '/var/www/projeqtor/tool/download.php' comment line 36 to 47 // include_once '../external/mailParser/Parser.p...

8 years ago
Reply
attached files on V7.0.0

Ticket #3266 recorded

8 years ago
Reply
Message on Activity

Hello, This message is not alarming. This is an indicator, check in menu Controls & Automation -> indicators.

9 years ago