You should, data could be refreshed.
HI, Have you thought to replan the planning ?
Hello, Please check on project screen if this project is not fixed or paused. ( a cell ticked on it) Otherwise, please give some more informations...
Good to know, Soon we will create a new alert when the predecessor wil ovestep the sucessor. As a meeting is settled once for all, decision to cha...
if i have well understood your question, i think so ! Lets' test it !
hi, it is posible to link a meeting to the end of an or severals activities with dependencies. On gantt it is visible On boards of dependencies bot...
Hello Global parmeters / WORK TIME / UNITS FOR WORK
HI, Sorry, no idea. it depends only on your habits, the way you work. Just an information, the workflow can progress without workload, it is just ...
Hi, To avoid misunderstanding, we should have written : calculation ( or recalculation ) of the left workload from this date. All left work over al...
HI, Yes Projeqtor is magic 😉 see below and go to it
You are welcome ! You can impact the planning by playing with the different planning modes.respecting constraints you gave. In your case : you ca...
if A) Only data written on valided : It keeps that to start to planify : so : expected ( valided) = planified = nice draws = nice Gantt = No forecas...
Hello, I cannot answer to you with so little information cause I do not understand what you are doing. But remember : Projeqtor is not a tool to d...
Hello Left work is always recalculated from the date you recalculate your planning. It seems so logical. FYI : BLACK NUMBER IN A WHITE CELL: impute...
hi On global parameter / Planning / 2nd line "show resource on Gantt" fill the field with your choice.
HI Fill the field " name of the user" on the resource screen. Result comes from it.
HI Very easy ! On list of tickets - go to multiple uptade ( a button on the list area) Select your tickets, choose the field to modify , select you...
HI, Please recalculate the planning. Then if it still like that it means that your resource is not planned somewhere else. There is no problem with...
Hello Financial / expenses / Budget
it's just a question of rounded numbers. this is not a bug. Could be improved.
HI, You can chose what you want. Projeqtor never says what is better or worst. All those solutions prove the richness of the tool . As for myself i...
hi You must replan even if the automatic planning button is actived when you come from the resource screen or any others screens which are not the ...
Hi, Did you check your rights on it as well as Administrator profil ?
HI Some KPI are made to show the evolution of single indicator. There is no data to follow on those bases. That is the reason why there is nothing ...
Hello, Very easy ! go on the list of resource. then go to multiple update ( a button on list area) , select all the resources, select your calend...